References
Company
/ Customer
Location
/ Date of construction
The work
Centrum Ptaszkowo
/ Agrosec
Grodzisk Wlkp.
2013
Mounting of maize dryer Stral FR12000 FR 8.
De Heus
Łomża
2013
Mounting of dosing silos feedmill factory - 4500 m3
Gospodarstwo Rolne A. Wasiluk
Zasiadki
2013
Mounting of grain storage silos- 4 x 100 t
Cargill
Białystok
2013
Modernization, weighing and packing line.
Piast
Gołańcz
2013
Installation pelleting line CPM 10 t/h in the feed mill factory
Best Oil
Lasocice
2013
Mounting of thermal isolation of transport equipment
Fermy Drobiu Woźniak
/ Buttimer
Ząbkowice - 2012
2013
Extention of the intake hall.
Cargill
Dobrzelin
2012
Repair and modernization work in feed mill plant.
Fermy Drobiu Woźniak
/ Buttimer
Ząbkowice Śląskie
2012
Mounting maize drying 65 t/h (Cimbria) and transport equipment.
Ekoplon
/ Drewmax
Grabki Duże
2012
Mounting of slide gate dosing and weights part of newly built feed mill plant.
Centrala Nasienna - Buttimer
Oborniki Wlkp. - Poland
2012
Installation of new seed cleaner.
Loulis Mills - Greece
Keratsini - Greece
2012
Mounting of silos for bran and flour.
Piast - Lewkowiec
Lewkowiec - Poland
2012
Dismantling of complete feed mills factory in Czech Republik and the relocation of the plant to the Poland.
Best Oil - Buttimer
Lasocice - Poland
2012
Installation of daily silo 850t and transport equipment of rape seed oil refinery.
Loulis Mills - Greece
Keratsini - Greece
2012
Installation of mill equipment- flourmill 300 t/24h.